Villa Dua and Tiga are starting to take shape.

4. 7. 2023

We've had five months of work under our belt and even though the rainy season hasn't exactly been kind to us, we've managed to get to the desired stage of construction, from which it's going to be smooth sailing.

So what stage are we at?

The steel structure of the ground floor, first floor and roof of Villa TIGA was completed. At the moment we are starting to pour the walls and also the visual concrete of the first floor.
In the forecourt of Villa DUA, the walls on the first floor have already been completed, including the preparation for the electrical installation. Installation (socket boxes and switches). The steel structure of the second floor and the roof are also now being completed.

And what next steps await us in the coming weeks?

We are also working on finishing the reinforcement and preparing the formwork for concreting both pools
As the next step, we are going to install the floor bond support system in the floor of both villas.
The next stage is to install the MEP preparation, i.e. the installation of the electrical pipes and water distribution.